27 March 2017

Plot 12: Construction update #2

Work has started in earnest on Plot 12, our £13 million new state of the art office building near to The Sadler Building.

What’s been happening?

Barnwood, our contractor, has been busy erecting the site fencing and setting up the site compound area.

More recently the groundworks have started and many of the foundations have now been poured.

Building’s branding

You might have noticed that the building’s new branding has been installed on the hoarding. We will be officially announcing the new name in the next couple of weeks.

Take a look

Viewing points have been installed in a number of places around the hoarding so feel free to take a look and keep an eye on progress.

What’s next

Over the coming weeks the foundations will be completed along with the construction of the lift pits.

The site will then be prepared for the arrival of the steel frame that will start to be erected from mid-April.

This will announce the start of the superstructure construction with work becoming clearly visible above the hoardings.

Should you have any questions, please email Robert Horsfield, Facilities Manager.

Construction update at The Oxford Science Park Plot 12 at The Oxford Science Park main exterior low res
Share